SR141 Improvements, I-95 to Jay Drive

Project Owner(s)

Delaware Department of Transportation

Construction Value

$75 Million

Location

Wilmington, Delaware

Project Schedule

April 2019 – December 2021

General Service Scope

Reconstruction of SR141 and SB I-95, involving complete interchange reconstruction, bridge reconstruction utilizing accelerated bridge construction through the use of Precast Sub Structure and Super structure elements. Complete widening and reconstruction of over 3 miles of SR141.

Project Challenge

Performing large scale construction on a congested roadway with significant utility obstacles.

Project Solution

Utilized Pierson’s experienced personnel to expedite construction and re-phase the project to work around utility impacts.